weekly planning

Weekly planning

Every week we plan ...

In the weekly TaskCycle planning we check: The planning then goes like:

"But we have to do ALL the things next week, not just what fits in the available time!"
You just determined what you can do and what you cannot do in the available time. So you now know that the other things will not be done anyway. The earlier you know that someting will not be done, the earlier you can do something about it, for example:

Don't waste your time thinking you can do more than you can do.

Find a more detailed explanation in booklet "How quality is Assured by Evolutiopnary Methods", chapter 6.1.
(see Booklet#2 on the downloads page)

  1. 2/3 is a default start value. This value works well in development projects. Change only if you experience that you should use an other value.